|

|
 |
12/27/99
- Started the initial
clean up.
- Supported structure
to start dismantling.
- Documented details
to restore to its original state.
01/07/00
- Gutted interior
walls and removed roof.
01/14/00
- Removed most of
the second floor exterior walls.
- Salvaged windows,
doors and trim.
- Started replacing
damaged floor joists.
- Dismantle fireplace
chimney.
02/04/00
02/07/00
- Reconstructed
upstairs knee walls on ell of building.
- Continued framing
roof.
- Started framing
exterior gable walls.
- Started reconstructing
upstairs interior walls.
02/14/00
After delays from
snow, sleet and rain
- Continued framing
roof and interior walls
- Completed framing
gable walls
- Started framing
front dormer
02/21/00
- Completed framing
roof
- Framed dormers
- Demo of furnace
chimney
02/28/00
- Continued upstairs
interior framing
- Started sheathing
roof
3/06/00
- Completed sheathing
roof
- Started porch roof
repair
- Started salvage
of exterior moldings
03/13/00
- Completed roof
sheathing
- Installed ice
& water shield, roofing felt and started shingling
- Started fasica
and exterior crown moldings
- Continued porch
repair
03/20/00
- Continued roofing
- Continued priming
and installing exterior molding
- Installed skylight
- Completed gable
sheathing and house wrap
03/27/00
- Continued exterior
trim
- Completed shingling
porch roof
- Started interior
trim prep
- Installed fire
stops
- Demo'd old furnace
- Completed shingling
roof
04/15/00
- Completed soffit
- Started construction
of chimneys
- Started gable clapboard
siding
- Started restoration
of windows
- Continued prepping
interior trim
04/21/00
- Completed furnace
chimney
- Continued construction
of fireplace chimney
- Started framing
upstairs interior walls
- Started prepping
siding for paint
- Continued restoration
of windows and trim
- Continued exterior
trim installation and restoration
04/28/00
- Completed furnace
chimney
- Continued construction
of fireplace and fireplace chimney
- Started framing
upstairs interior walls
- Started prepping
siding for paint
- Continued restoration
of windows and trim
- Continued exterior
trim installation and restoration
- Started door restorations
- Started electrical
rough-in
05/05/00
- Fireplace chimney
near completion
- Interior framing
near completion
- Started new duct
work for furnace
- Continued prepping
for paint
- Ordered new windows
- Continued restoration
of windows and doors
05/08/00
- Continued plumbing
- Rough-in insulated
exterior walls & ceilings
- Completed smoke
abatement
- Continued window
& door restoration
- Continued paint
prep
- Started installing
new windows
- Started patching
floor
06/16/00
- Continued plumbing
rough-in
- Continued installing
new furnace
- Continued drywalling
downstairs
- Continued exterior
painting
07/15/00
- Completed veneer
plaster
- Continued interior
trim
- Started priming
interior walls & ceilings
- Plumbing completed
except for fixtures
- Completed replacing
damaged or missing hardwood flooring
07/29/00
- Completed interior
trim
- Completed hanging
interior doors
- Continued interior
painting
- Completed electrical,
plumbing & masonry
- Installed kitchen
cabinets
- Started delivery
of appliances
- Started sanding
hardwood floors
- Installed closet
rods & shelves
- Continued restoration
of stairs
8/05/00
- Stained and polyurethaned
upstairs floors
- Restored railing
- Replaced fireplace
mantel
- Continued sanding
downstairs floors. Almost complete and ready for stain and polyurethane.
- Installed bath
exhaust fan duct
- Started final
clean-up
9/2/00
- Constructed new
Bilco door
- Installed built-in
shelves in pantry
- Restored porch
apron
- Installed additional
lighting in stairway
- Completed punch
list
- Job finalized except
for change orders
|
|
|