lighthouseDyce Head Lighthouse Keepers House Restoration Project

 

Dyce Head Lighthouse Keepers House
Restoration Project

Weekly Progress Report

Dec | Jan | Feb | Mar | April | May | June | July | August | September

12/27/99

  • Started the initial clean up.
  • Supported structure to start dismantling.
  • Documented details to restore to its original state.

01/07/00

  • Gutted interior walls and removed roof.

01/14/00

  • Removed most of the second floor exterior walls.
  • Salvaged windows, doors and trim.
  • Started replacing damaged floor joists.
  • Dismantle fireplace chimney.

02/04/00

  • Started re-framing roof.

02/07/00

  • Reconstructed upstairs knee walls on ell of building.
  • Continued framing roof.
  • Started framing exterior gable walls.
  • Started reconstructing upstairs interior walls.

02/14/00

After delays from snow, sleet and rain

  • Continued framing roof and interior walls
  • Completed framing gable walls
  • Started framing front dormer

02/21/00

  • Completed framing roof
  • Framed dormers
  • Demo of furnace chimney

02/28/00

  • Continued upstairs interior framing
  • Started sheathing roof

3/06/00

  • Completed sheathing roof
  • Started porch roof repair
  • Started salvage of exterior moldings

03/13/00

  • Completed roof sheathing
  • Installed ice & water shield, roofing felt and started shingling
  • Started fasica and exterior crown moldings
  • Continued porch repair

03/20/00

  • Continued roofing
  • Continued priming and installing exterior molding
  • Installed skylight
  • Completed gable sheathing and house wrap

03/27/00

  • Continued exterior trim
  • Completed shingling porch roof
  • Started interior trim prep
  • Installed fire stops
  • Demo'd old furnace
  • Completed shingling roof

04/15/00

  • Completed soffit
  • Started construction of chimneys
  • Started gable clapboard siding
  • Started restoration of windows
  • Continued prepping interior trim

04/21/00

  • Completed furnace chimney
  • Continued construction of fireplace chimney
  • Started framing upstairs interior walls
  • Started prepping siding for paint
  • Continued restoration of windows and trim
  • Continued exterior trim installation and restoration

04/28/00

  • Completed furnace chimney
  • Continued construction of fireplace and fireplace chimney
  • Started framing upstairs interior walls
  • Started prepping siding for paint
  • Continued restoration of windows and trim
  • Continued exterior trim installation and restoration
  • Started door restorations
  • Started electrical rough-in

05/05/00

  • Fireplace chimney near completion
  • Interior framing near completion
  • Started new duct work for furnace
  • Continued prepping for paint
  • Ordered new windows
  • Continued restoration of windows and doors

05/08/00

  • Continued plumbing
  • Rough-in insulated exterior walls & ceilings
  • Completed smoke abatement
  • Continued window & door restoration
  • Continued paint prep
  • Started installing new windows
  • Started patching floor

06/16/00

  • Continued plumbing rough-in
  • Continued installing new furnace
  • Continued drywalling downstairs
  • Continued exterior painting

07/15/00

  • Completed veneer plaster
  • Continued interior trim
  • Started priming interior walls & ceilings
  • Plumbing completed except for fixtures
  • Completed replacing damaged or missing hardwood flooring

07/29/00

  • Completed interior trim
  • Completed hanging interior doors
  • Continued interior painting
  • Completed electrical, plumbing & masonry
  • Installed kitchen cabinets
  • Started delivery of appliances
  • Started sanding hardwood floors
  • Installed closet rods & shelves
  • Continued restoration of stairs

8/05/00

  • Stained and polyurethaned upstairs floors
  • Restored railing
  • Replaced fireplace mantel
  • Continued sanding downstairs floors. Almost complete and ready for stain and polyurethane.
  • Installed bath exhaust fan duct
  • Started final clean-up

9/2/00

  • Constructed new Bilco door
  • Installed built-in shelves in pantry
  • Restored porch apron
  • Installed additional lighting in stairway
  • Completed punch list
  • Job finalized except for change orders